Our projects range in size from a Service Call of less than $100 to a $1.2MM Tier III Data Center. We have successfully completed our work using the design-build, design-assist, and bid-build project delivery methods. Geographically, our focus is on the Denver Metro market but we serve the Healthcare, Pharma/Biotech, Manufacturing, Education, Worship, Retail, Entertainment, Education, Residential, and Data Center markets for the entire state of Colorado. In special circumstances, we have traveled to other states with long-standing, repeat customers.

Job Name Customer Contract Amount Start Completion Work Description
EPWI EPWI $771,235 May-10 Feb-11 Solar PV install
Target roll out MTG $156,000 May-10 Jul-10 Video game kiosk roll out in numerous stores
Pepsi Center Pepsi Center $75,000 Jun-10 Aug-10 New scoreboard wiring
PERA PERA $185,000 Oct-10 Dec-10 7th floor data buildout
Trust Company of America Trust Company $1,037,000 Jan-11 Jul-11 Design/Build Data Center Critical Power Upgrade
Jeffco Libraries – Sorters Kennerly Construction $45,390 Mar-11 Oct-11 Wire new conveyor system
Jeffco Library Admin Jeffco Library $40,844 May-11 Oct-11 Remodel admin building
Garden Terrace Apts Garden Terrace $22,000 Jul-11 Oct-11 New exterior lighting
Atlas Copco machinery Atlas Copco $23,900 Oct-11 Oct-11 Rewire mining machinery
Xcel smart meter rollout Honeywell $273,043 Apr-12 Jul-12 Install residential smart meters
Penny Flats BluSky Restoration $226,772 Mar-12 Oct-12 Mixed use condo/commercial building
Yard House Dickinson Cameron $201,259 Feb-12 Jun-12 Restaurant/Bar tenant improvement
Park Lane RK Mechanical $132,293 Mar-12 May-12 Replace building service and feed new chiller
GO Fiat Commercial Building Services $174,872 Aug-12 Dec-12 Design/Build new car dealership
GO Hyundai Commercial Building Services $249,522 Jun-12 Nov-12 Design/Build new car dealership
GO GMC Commercial Building Services $363,242 Mar-12 Aug-12 Remodel existing car dealership
Pepsi Center Preaction Simplex $31,382 Jul-12 Sep-12 Wire fire alarm preaction system
Heat Trace Allied Waste $77,144 Sep-12 Nov-12 Provide heat trace at waste facility
FedEx Lighting retro American Energy $24,707 Feb-12 Mar-12 Retrofit warehouse lighting
King Soopers Warehouse Arbon $77,144 Apr-12 Jul-12 Wire new dock equipment
Colorado Springs Country Club Excel Associates $75,584 Mar-12 May-12 Remodel hotel
Jubilee Fellowship Church Nehemiah $52,335 Mar-12 Jun-12 Church remodel
Move data center Colorado PERA $49,596 Jan-12 Mar-12 Move data cabling for data center relocation
United Presbyterian United Presbyterian $60,856 Mar-12 May-12 Install new Smoke detectors and CO detectors